The system had gone live after a bit of delay; everyone
sighed in relief and believed that the best is yet to come with the long
awaited solution that should deliver a competitive edge before others caught
up. The system automated processes that were thus far manual and in a geographically
spread business where collation of data took some effort; standardization using
spreadsheets had not delivered the desired result. Thus anticipated benefits
from the system were high as the deployment completed as per timetable.
Giving some credit to the implementation team comprising of
business, IT and the vendor, they had attempted supporting the business to
institutionalize the effort. Time passed by, the usage graph gradually started
declining reaching a level that rang alarm bells. Response time was the first
issue raised followed by bugs, functionality limitations, lack of reports and
analytics, it appeared that everything that could go gone wrong had. The
challenge was thrown to the new IT leadership team to diagnose and fix.
A crack team was created to deep dive, assess and document
the root cause and find a solution to the predicament that faced the
enterprise. The team spent more than a month meeting members from IT, business,
vendors, software principal, and key users collating information that would
finally create the prescription to remedy the situation. The laundry list thus
created needed budgetary support and resources to get started; so the CIO
sought audience from the business head and the CFO.
With aplomb the CIO personified in most meetings, he
presented the findings to the assembled group. It was more than a year since
the solution had been deployed; barring basic functionality, users had stopped
using it, reverting to time-tested quasi manual process. The investment had
failed to deliver commensurate benefit. Fair evaluation of the solution had
reported 85% fitment to requirements. The implementation partner recommended by
the principal had struggled but finally delivered the desired solution.
As the discussion progressed there was growing discomfort in
the room as the list of changes appeared unending. It challenged conventional
wisdom to implement any solution with minimal changes or customizations. The
CIO pushed a long list of 117 changes to the COTS solution over and above those
done as a part of the original implementation promising everything the business
wanted. The ask was budget almost equal to the total project cost thus far and
timeline spread over more than a year.
For the business head and the CFO the decision was between
scrapping the project and putting time, effort and money to rescue the project
which promised significant operational and process improvements. The conviction
of the CIO swung it in favor of putting some more money behind the challenged
project. The business team was asked to prioritize the long list by putting it
into different buckets based on impact and effort. The budget was scrutinized
by the Finance team and the list of 117 changes was approved.
Quick wins came easily, re-use of the solution jumpstarted
with delivery of the high priority items on the list. Emboldened the team
pushed ahead only to face roadblocks on technology as well as stability of the
changes. Three quarters later the list was pruned and the internal and
outsourced development team given the stick; the business disengaged from
active participation deciding to get involved whenever a delivery happens. The
project was relegated into the background keeping the team busy, often pulled
out for other pressing activities.
The now floundering project became the white elephant in the
room in review meetings with IT. The CIO exited under mysterious circumstances
replaced by young blood; triggered by a strategic review conducted by a veteran
consultant, rational thought and direction on the project finally saw light of
day with the approval of an alternative solution to replace the infamous mess. News
of scrapping of project created flurry of activity; the Principal vendor sought
to intervene, a request that was promptly denied.
Where did the project go wrong ? Initial evaluation was
extensive and could not be faulted; the now approved new solution came across
as the winner; the incumbent solution was the next best choice by a small
margin functionally but at half the cost making it an attractive option to
consider. Are next best choices not good enough ? Was the implementation flawed
or people competency a challenge ? Was the CIO correct to push for large number
of changes ? Why did he not propose the other solution ?
At times people are blind to right choices; they push low
cost or safe choices, or put good money behind bad as was this case with
irrational prevailing; the CIO avoided conflict by not confronting past
decisions and thus lost the opportunity to create better outcomes. Compulsions
if any remain a mystery between the business head and CIO. Opportunity lost,
time, effort and money wasted, the enterprise is the final loser. I don’t
believe that many would approve such elaborate customization, but I may be
wrong !
Well put...its the management push to find short term solutions instead of being patient and getting to long term solutions...you are right CIO should push back, but then the business does not have the maturity to understand why department head is pushing back. instead they pin him down to do what they feel is right and let the subject matter expert take a back seat...
ReplyDelete